Woking

  • Contractor McAlpines

  • ArchitectBenoy

  • Structural EngineerHaskin Robinson Waters

  • Value£32m

  • Contract Period24 months

  • DetailsThe works under the Main Contract include for the design and construction of 392 residential units in two superstructure tower (from the podium); a 190 bedroom four star hotel; approximately 120,000 ft2 of new retail and new parking decks.​

    8 storey shared podium, across the entire footprint of the site, with large transfer beams to facilitate superstructures and large clear-span area​.

    Superstructure towers formed using slipform and jumpform systems, with climbing screens to the superstructure perimeter. ​

    Getjar programme review highlighted the need to advance the cores ahead of the podium and superstructure floor plates, to remove the core from the critical path (and allow the main contractor to relocate the cranes onto the cores).​